Event |
|
Union Cabinet approved the Revised Cost of DRIP amounting to Rs. 3466 Crores along with two years extension. The scheduled closure of DRIP is now June 2020. Also, CSMRS, N Delhi and CWPRS, Pune have been considered for capacity building under Central Component. |
The Union Cabinet approved Revised Cost Estimate of ongoing DRIP Project from Original RS. 2100 Crore to Revised Cost of Rs. 3400 Crore with extension of two year for project completion. The revised Closure of DRIP is now June 2020. Also, participation of two Central Agencies i.e. CSMRS, New Delhi and CWPRS, Pune has been approved. |